Project History
In June 2007, Excelaron filed an application for a Conditional Use Permit to drill, test and produce four oil wells on an existing oilfield on Mankins’ Ranch. After preparation of the Initial Study, the County issued a Mitigated Negative Declaration in February 2009. In response to concerns expressed by the public, Excelaron agreed to prepare an Environmental Impact Report (EIR). The EIR process is now underway and will analyze potential project impacts and propose mitigation measures where necessary.
The Environmental Impact Report
The main purposes of the EIR include:
The County has selected Marine Research Specialists (MRS) and their consultants to conduct the environmental review, which will examine the following issue areas in detail:
MRS will follow the California Environmental Quality Act (CEQA) Guidelines issued by the State Office of Planning and Research, and the County’s EIR standards, practices, and guidelines to complete the EIR. CEQA is considered the most stringent environmental review process in the country.
MRS will complete numerous technical reports and studies, as well as provide a peer review of the informational material prepared by Excelaron’s consultant team. A list of those studies can be reviewed at www.excelaron.net
Opportunities for Public Review and Input
There have been numerous opportunities for public input on the project since it was first proposed in 2007, and there will be several additional opportunities for input throughout 2010 as the EIR is completed. Currently, a public scoping meeting on the issues to be analyzed in the EIR is scheduled for March 29th in Arroyo Grande. This will be the sixth public comment meeting for this project to date. Prior public outreach efforts were conducted by Excelaron, County Supervisor Katcho Achadjian, the County Planning Department and the City of Arroyo Grande. There will be at least one additional scoping meeting, a 45-day public review period of the draft EIR, two public workshops, and ultimately a public hearing before the County Planning Commission.
Timeline for Completion
The draft EIR is tentatively scheduled to be completed by August 6, 2010. The chart below highlights the projected timing of key milestones and deliverables during the EIR process.
Milestone |
Date |
Draft EIR Style Guide to County |
March 1, 2010 |
Draft Project Description to County |
March 11, 2010 |
Draft Cumulative Project Descriptions to County |
April 7, 2010 |
Draft Environmental Setting Sections to County |
April 22, 2010 |
Administrative Draft EIR to County |
June 14, 2010 |
Release of Public Draft EIR (45-day public comment period) |
August 6, 2010 |
Public Workshop on EIR |
TBD |
Public Comment Meeting on EIR |
TBD |
Administrative Final EIR and Response to Comments to County |
October 25, 2010 |
Final EIR to County |
December 10, 2010 |
Source: Marine Research Specialists